One of the big differences between domestic and commercial solar system design is the use of cable tray and in this presentation we will look at the use of cable tray on the roof of a large distribution warehouse that houses a commercial solar array.
The tray in this example is used to accommodate the over 100 DC cable runs.
We take a spreadsheet approach that allows the designer to assign a particular name to a particular cable tray run, calculate how much tray, tray lid and associated materials required for each individual run and the overall amount.
We will be using Excel but any spreadsheet will work so let’s get started!
We will configure the spreadsheet into a series of columns the first being Row number, second will be Roof description, third, length of tray and fourth the width of tray used.
Let’s continue on. The next series of columns includes:
Run length, lid length and Lid overlap in mm are self explanatory. The Buffer % is to allow for mistakes and unknowns, e.g. 4% adds 4% to the run length.
Basically the inputs for each cable tray row can be dragged down.
Next inputs include:
With the ‘what pieces are you using’ , we see our first formula that references the selected tray’s width and adds a certain amount, in this case, 80 mm to accommodate the cable tray hold downs.
Now the outputs replicate the first 2 x columns from the inputs but the third column here uses a formula to calculate:
Tray lengths references the cable tray run and divides by the length of tray used and then rounds up.
This also happens with the lid BUT the length is reduced by the amount of overlap.
Hex screws references the spacing input and the cable tray run and adds two and the splices are the same as panel mid clamps, number of trays minus 1 x 2.
The next three columns use the number of splices figure:
The next three columns use the number of supports figure:
These all relate to the number of structural supports under the tray
Next on the list is:
Length left over can be used to gauge waste and also if minimum waste is => than minimum length required for a smaller width tray it can be used.
So we have the outputs for all the rows and now we need to know the total material list for this project cable tray wise.
As there are a few different tray profiles we need to know the totals.
The formulas to ‘gather up’ all the info are as follows:
This section outputs the smaller bits and pieces ranging from the number of splices all the way through to no. of washers for channel nuts.
Note: these calculations are independent of the width of the tray as this is irrelevant.
What if we quickly wanted to know what tray was being used on what row and the totals for those rows.
For example, a 450mm tray. For this we use data validation, the drop down list, filter and the sum function.
What about a 300mm tray?
600mm tray?
On big commercial solar projects the ability to accurately calculate material costs is a decided advantage and cable tray is no exception. In this presentation we looked at how to approach this problem from a spreadsheet perspective and the same logic can be applied to other aspects of your next commercial solar project..
If you’d like to see what Greenwood Solutions get up to in the real world of renewable energy, solar, battery storage and grid protection check out our industry and commercial pages:
https://www.greenwoodsolutions.com.au/industry
https://www.greenwoodsolutions.com.au/commercial
https://www.greenwoodsolutions.com.au/news
https://www.greenwoodsolutions.com.au/commercial/customer-stories