Custom Float Design
~650 solar panels were secured to floats - a practical but clever design, which meant the team avoided contact with the wastewater
Launch dock construction
A special dock needed was built - one that enabled our people space enough to build and deploy the floats with efficiency
Mooring Installation
Precision handling of a 250-tonne crane was needed when positioning the concrete anchors more than 68 metres from shore. Did we mention each of the anchors weighed in five tonne?!
People First
We go on about it, but we’ll apologise for ensuring the safety of Greenwood’s People. The entire installation process was achieved without any direct contact with the wastewater. An insane feat!